Custom clearance.
Receiving wind turbine equipment under hook at Imported Port, and trucking to storage yard at port.
Storage of wind turbine equipment at Port.
Load wind turbine equipment on to truck from storage yard and trucking to load onto barges.
Transporting wind turbine equipment by barges from Imported Port to Hoa Dong 2 Wind Farm Project in Soc Trang.
Unload wind turbine from barge to truck and trucking from project’s temporary jetty to project’s storage yard.
Storage of wind turbine equipment at the project’s storage yard.
Load wind turbine equipment onto trucks from storage yard and trucking to each wind turbine’s position at the project site.