Transport steel pipe piles (17-30m) from factory in Dong Nai to jobsite in Hai Phong
Building a new international deep-sea port and related basic infrastructure in Lach Huyen area.
INVESTOR: Ministry of Transport of Vietnam
INVESTED CAPITAL: VND 25.17 trillion
CONSTRUCTION PERIOD: 2013-2017
- Trucking from Factory to port of loading in Dong Nai
- Loading from trailer onto vessel
- Inserting dunnage and lashing on vessel
- Transport from Dong Nai Port to Hai Phong Port
- Unloading from vessel onto trailer
- Trucking from Hai Phong port to Jobsite
Steel Pipe Piles, Length: 17-30m, OD: 800-1100mm
Total: 1,228 pcs / 9,500 tons