Transport 12 sets of wind turbine's blades by barge for the project of HBRE Chu Prong WPP

Client: HBRE Chu Prong Gia Lai Wind Power Project
Time: June 2021 - July 2021
Home » Energy & Power

Scope of works:

- Loading blades at port
- Dunnage and lashing for blades on specialised barge
- Transport blades by barge from Quy Nhon Port, Binh Dinh Province to Phu My, Ba Ria Vung Tau province
Then we will do inland trucking for these blades from Phu My to the Project site for erection, which helped complete the turbines' equipment so as for the wind power plant to operate in time.

Technical specifications:

- Blades' length: 76.3m, width: 4.95m, height: 3.4m
- Quantity: 36 units of blades

Project Details:

vận chuyển thiết bị điện gió cho dự án HBRE Gia Lai

vận chuyển thiết bị điện gió cho dự án HBRE Gia Lai

vận chuyển thiết bị điện gió cho dự án HBRE Gia Lai

vận chuyển thiết bị điện gió cho dự án HBRE Gia Lai

vận chuyển thiết bị điện gió cho dự án HBRE Gia Lai

SEND A REQUEST

Fill an request form to get more details about our services and our capabilities.